The local computer room was completed last Friday. All power is ready under each of the 21 rack positions. Each rack position has 4 CAT6 cables connected to the networking rack which can be seen. Other things completed were; ceiling lights, painting, smoke detection system, and door fitting.

On Monday 10th two existing compute racks were installed and two empty racks for the cluster upgrade arrived. A rack full of worker nodes for the existing grid cluster can be seen and is up and running.

Today the servers arrived from Viglen and installation has commenced.